Under Power control, you can view and configure settings for active and reactive power control of your plant. A bluelog Neo with a PV, Battery, or Hybrid control license is required to carry out power control functions.
Power control: basic approach
The following is one possible setup workflow. If you do not carry out the steps in this order, power control may not function properly.
-
Configure plant data for PV, battery, or both.
-
See Plant data.
-
-
Plan your master-slave setup.
-
See Controller operation.
-
-
Configure active power and reactive power (if applicable).
-
See Active power and Reactive power.
-
-
Activate power control.
-
Check one of the following to confirm that power control is working properly:
-
Power Control > Overview
-
Cockpit > Charts: Select the relevant values and view them in the chart.
-
Caution
Activate the Power Control toggle at the top of the Active power and Reactive power pages ONLY after you have fully configured your power control setup.