Under Power control, you can view and configure settings for active and reactive power control of your plant. A bluelog Neo with a PV, Battery, or Hybrid control license is required to carry out power control functions.

Power control: basic approach

The following is one possible setup workflow. If you do not carry out the steps in this order, power control may not function properly. 

  1. Configure plant data for PV, battery, or both.

  2. Plan your master-slave setup.

  3. Configure active power and reactive power (if applicable).

  4. Activate power control.

  5. Check one of the following to confirm that power control is working properly:

    • Power Control > Overview

    • Cockpit > Charts: Select the relevant values and view them in the chart.

Caution

Activate the Power Control toggle at the top of the Active power and Reactive power pages ONLY after you have fully configured your power control setup.